CASE 04

·

Project cargo

·

Energy & Industrial

Four 72-metre monopiles, Rotterdam to Taiwan without a single re-stow

Four monopile foundations shipped on a heavy-lift vessel from Rotterdam to Taichung, with lift, lashing and discharge planned around the installation schedule.

NLRTM

Rotterdam, NL

Heavy-lift charter · 43 days

TWTXG

Taichung, TW

NLRTM

Rotterdam, NL

Heavy-lift charter · 43 days

TWTXG

Taichung, TW

Steel monopile sections staged on a port quay beside a container terminal

SHIPMENT MANIFEST

Client

Offshore wind foundation contractor

Cargo

Four steel monopiles, up to 72 m long

Mode

Project cargo

Industry

Energy & Industrial

Handled by

Rotterdam

Completed

May 6, 2026

OUTCOME

Heaviest unit

1,280 t

Port to port

43 days

Re-stows

0

01

The challenge

An offshore wind contractor needed four monopile foundations delivered from Rotterdam to Taichung in time for an installation campaign. Each monopile was up to 72 metres long, the heaviest weighed 1,280 tonnes, and the installation vessel’s schedule left little margin for delay.

02

Constraints

  • Units too long and heavy for anything but a heavy-lift vessel

  • Load spreading and sea-fastening designed for a long ocean passage

  • Discharge only possible at a quay rated for the loads

  • Routing via the Cape of Good Hope

03

Operational plan

We chartered a heavy-lift vessel with twin cranes able to lift the units in tandem. Our engineering partner prepared the lift plans, stowage and sea-fastening design, which were reviewed by the vessel operator and a marine warranty surveyor before loading.

The stowage plan loaded the four monopiles in reverse discharge order so none would need to be moved during the voyage or at discharge.

04

Key decisions

  • Heavy-lift charter instead of breakbulk liner space, to control the schedule

  • Discharge order fixed in the stowage plan

  • Sea-fastening signed off by a marine warranty surveyor

  • Arrival window agreed with the installation contractor

05

Outcome

The vessel sailed on schedule and arrived in Taichung after 43 days, via the Cape of Good Hope. All four monopiles were discharged in sequence with no re-stows and handed over for installation.

FROM THE OPERATION

Installed offshore wind turbines on yellow foundation transition pieces
Monopile sections lined up on the quayside ahead of loading
Offshore wind farm at sea, the destination for foundations like these

“

They told us on day one where the risk sat on the lane — and then removed it.

Logistics Director, offshore wind developer (demo)